Posts under ‘Highway 50 update’

Highway 50 update Nov. 17, 2023: Final stage to begin Tuesday

The final stage of construction will begin on Tuesday, November 21!  Stage 6 involves finishing work on the north and south sides of the street.   A single lane of traffic in each direction will be maintained, with all traffic on the inside lanes of the newly paved roadway.  Access to all businesses will be maintained and all […]

Highway 50 update July 28, 2023

Bidirectional traffic has been shifted to the South side of STH 50 on the new concrete pavement and paved temp asphalt. EB Left Turn Lanes at STH 75, 246th, and 236th. WB Left Turn Lanes at 242nd, 244th, 246th, STH 83, and CTH F. All side roads are open for bidirectional traffic. Current Construction Activities […]

Highway 50 update April 10, 2023

Stage 2 Construction Work & Traffic Configuration continue to progress.  Project officials anticipate this configuration will be in place through June.  A more detailed timeline as the transition to Stage 3 gets closer. Traffic Updates Wednesday 4/12/23:  246th Street South leg will be CLOSED to traffic all day.  All access to Westosha Central High School will be provided at […]

Highway 50 update March 19, 2023

Weather conditions continued to delay the start of Stage 2.  Officials expect that it will begin sometime mid-week, but it will not be starting on Monday.  Snow, rain, and cold temperatures are not good conditions for laying new pavement or installing temporary pavement markings.  Pavement marking tape and paint can quickly deteriorate if installed during […]

Highway 50 update March 5, 2023

What was done week of Feb. 27: Stage 1B removals have begun at STH 83 and 246th Ave intersections. Outdoor Lighting Construction has started installation of temporary signals in both intersections.  Crews using small amount of drums in the corners of the intersections for traffic control. TCP will begin to stage traffic control devices for Stage […]