250th Avenue reconstruction project set for mid-November completion


View Larger Map
Paddock Lake residents living with the reconstruction of 250th Avenue have a few more weeks to cope with the inconvenience of the project.

At this point, the project should be completed by mid-November, said Greg Boldt, village engineer from Baxter & Woodman.

That of course, depends on weather. The project did benefit from a 10-day period of very good weather already, Boldt said.

Trustee Joe Riesselmann asked about the state of the road by Halloween. Boldt said a preliminary layer of paving may be done by that time, again depending on weather. It is unlikely the final layer would be done by then, however.